What approval procedures are required for the construction of commercial and industrial energy storage stations?
To install a commercial or industrial energy storage station, it is necessary to conduct project registration on the local development and reform bureau's website and apply to the local power company for a power connection approval. Additionally, according to specific regulations in different regions, other procedures such as fire design review, environmental impact assessment report, and case evaluation report may also be required.Therefore, before the project starts, it is necessary to thoroughly understand the acceptance and review standards for commercial and industrial energy storage projects in the local area, and make preparations for the project's preliminary budget. All these procedures are handled by the integrator, while the owner only needs to cooperate in providing the required materials.
1、The site should be located outdoors, and it is preferable to choose a location that is far away from the office area and densely populated areas, and there should be no hazardous chemical warehouses within 10 meters.
2、 Select a location that is relatively close to the distribution room of the access point (preferably within 30 meters) and is convenient for cable arrangement.
3、 Consider a hardened site that is convenient for transportation, lifting, and capable of bearing loads. For actual projects, safety protection passages and isolation passages should be reserved in accordance with the requirements of the local fire department.
4、For the user's internal site or adjacent areas, the adjacent areas should be adjacent to the enterprise's fence. There should be no public roads or other buildings separating them.
What information does the owner need to provide when installing a commercial or industrial energy storage facility?
Before installing a commercial or industrial energy storage station, the owner needs to provide information such as the enterprise's property rights, electricity load, electricity usage situation and electricity equipment for the corresponding project. Technicians need to use the enterprise's electricity load data, average/maximal power of the load and transformer capacity and load data to calculate the capacity of the energy storage system.
In addition, the owner needs to provide information such as the primary power system diagram, the plant layout plan, the distribution room layout diagram, and the cable routing direction, etc., to determine the construction location of the energy storage station and the position of the connected transformer.
The industrial and commercial energy storage market is currently in a period of vigorous development, with its scale continuously expanding. During this process, the safety and economy of energy storage project construction have always been the focus of attention in the industry and society. This article aims to systematically analyze and answer the common problems encountered in the design and construction of industrial and commercial energy storage stations, and it is provided for reference and learning by everyone.